Courtyard Gardens Oxted

Oxted Gasholder - Courtyard Gardens Build - November 2019

Dave and Kieran groundworks foremen are standing on a pile cap, part of the foundation of what will be one of the pillars in the underground car park, this is part of what supports the entire building!

Dave and Kieran groundworks foremen are standing on a pile cap, part of the foundation of what will be one of the pillars in the underground car park, this is part of what supports the entire building!

Welcome to my November blog here at Courtyard Gardens, Oxted, the former site of the gasholder.

This is where construction is taking place to build 111 luxury apartments. Each month, since January 2019 I have been visiting to photograph the progress for posterity, with the kind permission of St William, part of the Berkeley Group.

Each and every time I arrive I learn something new. I am always fascinated by all the processes that are taking place. If like me, you know very little about the construction process, or you are one of the many buyers of the one, two, or three-bedroom apartments and penthouses; or you are just curious to know more, then these blogs are written with you in mind and others too.

These photographs were taken on Friday 15 November, they each have a description on to tell you more about what’s taking place.

Read on to discover more…

The pilings process is coming to an end and we will soon start to see progress above ground once building works start to take place in the new year.

Workmen and engineers start work from 8am until 6pm every weekday with additional time most Saturdays. Flood lighting is used from 4pm at this time of year so as not to lose any valuable working hours.

This is a relatively small site for the Berekely Group who are use to working on huge developments all over the country, with many different challenges, such as working near the River Thames and other urban areas that are in close proximity to cities and skyscrapers

The numerous deliveries that arrive everyday are carefully planned so as not to cause too much disruption to the high street, or the work onsite as well.

As mentioned on previous blogs the foundations are for three Blocks - A, B and C all with outside space and underground parking.

If you would like to take a look at a model of the completed development, this can be found at Robert Leech Estate Agents on Station Road East, Oxted who will be more than happy to show you the finished look.

This is a Dust Scanner to monitor the dust particles in the air. Air quality and vibration monitoring are in place around the site and will continue to take place throughout the build process, which completes in summer 2021.

This is a Dust Scanner to monitor the dust particles in the air. Air quality and vibration monitoring are in place around the site and will continue to take place throughout the build process, which completes in summer 2021.

That’s about it for my November visit, I’ll be back in December with a new update.

To read my previous ten blogs this link takes you to the Blog page on this website.

This link to Robert Leech Estate Agents website shows you more about the finished development.

Bye for now.

Stella

To read other previous blogs these can be found on the ‘Featured’ blogs below by using the arrows on the right to scroll through the past 30 blogs.

 

Oxted Gasholder - Courtyard Gardens Build - October 2019

Welcome to my October blog (number 10) about the construction process at Courtyard Gardens, the former gas holder site here in Oxted.

Regular readers will be aware that I have taken on this personal project to visually document the construction process from the demolition of the gasholder back in January to completion in summer 2021.

My monthly visits to the site are accompanied by Ness Kingham, Assistant Site Manager for St William part of the Berkeley Group, who shows and tells me more about the progress every time. I am always in awe of the vastness of the development and all the processes that are involved, it looked so small when it was overgrown with trees surrounding the gasholder.

These photographs with descriptions on each were photographed on 22 October 2019.

The site from the top corner nearest the railway station, looking down towards the former Johnsdale car park.

The site from the top corner nearest the railway station, looking down towards the former Johnsdale car park.

During this visit, the completion of the piling was well underway, with over 300 holes drilled by the auger, the drill attachment on the piling rig. It was interesting to watch the final few holes being drilled and filled with the basket type ‘cage’ and concrete. When the process is complete it is marked with a triangular ‘witches hat’ during the drying process so it is easy to identify its location.

 

Around the perimeter of the site is a narrow walkway to enable access from the top to the bottom.

The site has two entrances which enables carefully planned site traffic to enter and exit at strategic times. These entrances are independent of each other, you can only exit from the one you entered, this will remain the same for the residents of Courtyard Gardens.

Well, that’s it for the October edition of my blogs, I’ll be back next month with an update from my November site visit, I think it will start to look very different with works more visible above ground level.

To read my previous 9 blogs this link takes you to the Blog Page on the website.

Bye for now.

Stella

To read other previous blogs these can be found on the ‘Featured’ blogs below by using the arrows on the right to scroll through the past 30 blogs.

 

Oxted Gasholder - Courtyard Gardens Build - September 2019

On the left the auger on the piling rig that drills out the ground to make way for the concrete.

On the left the auger on the piling rig that drills out the ground to make way for the concrete.

Welcome to my September blog about the St William (part of the Berekeley Group), housing development for 111 luxury apartments at the former gasholder site here in Oxted.

Regular readers of my blogs will be aware that since January this year I have been photographing the demolition of the gasholder and the start of the building process to visually document the history for posterity, due for completion summer 2021.

Each month I am given access to the site, accompanied by Assistant Site Manager, Ness Kingham who escorts me and tells me about the progress since my last visit. I am always fascinated by the processes and developments, I have learnt so much!

This is just the beginning of the building process of 3 blocks - A, B and C where the sheet piling has taken place and bearing piles on block C on the former Johnsdale car park are complete.

Over 5500m3 of soil has been removed from the site to date, that’s the equivalent volume of more than two Olympic sized swimming pools! The removal of the contaminated earth resulting from the former gasworks is also complete.

The photographs on this blog were taken on Monday 16 September 2019 and tell the story with captions on each image. I have watched an auger drill into the ground and deposit concrete for the bearing piles to take place, read on to find out more.

Each image has a caption on describing the processes.

The piling rig is a fascinating piece of machinery and capable of so much very efficiently.

To read previous blogs please click this link, this is blog number 9.

Each time I visit the site so much has changed, it really is beginning to take shape for the next stage of the building process.

Thank you for reading this recent blog, I hope you have found it interesting. I’ll be back in November with an update from my October visit.

To become a regular subscriber to my monthly round-up blogs simply scroll down to the bottom of the page and click on the ‘subscribe to our newsletter’ button.

See you next month!

Stella

To read other previous blogs these can be found on the ‘Featured’ blogs below by using the arrows on the right to scroll through the past 30 blogs.

 

Oxted Gasholder - Courtyard Gardens Build - July 2019

The sheet piling is taking place for the construction of all 3 Blocks, A, B & C, this photograph was taken on 17 July 2019,

The sheet piling is taking place for the construction of all 3 Blocks, A, B & C, this photograph was taken on 17 July 2019,

Welcome to this months July blog about the progress at the St William, Courtyard Gardens development here in Oxted, this blog is number 7, previous ones can be found here.

For my regular readers and locals, you will be aware that the gas holder that once stood on this site for over 50 years was deconstructed earlier this year, its removal has made way for the construction of 111 luxury apartments due for completion summer 2021, my regular monthly blogs will keep you updated about the progress over the next two years.

This month I attended the site on July 17th, one of the hottest days of the year and the ground was dry and relatively easy to walk on, which compared to my visit in June when there was so much rain fall it had to be pumped away and the ground was very wet and slippery.

My past visits had all taken place on overcast and cold days, it was interesting to visit on a day when the sun was beating down as it made me realise how exposed the site is and how the people working on site need to have regular breaks and drink lots of water to prevent dehydration, I felt drained and I had only been on site for 45 minutes before 9.30am!

Machinery and operatives working on the insertion of the sheet piling, during July 2019.

Machinery and operatives working on the insertion of the sheet piling, during July 2019.

The apartments are being built in 3 separate Blocks - A, B & C - Block C which sits north of the former Johnsdale car park has had the sheet piling inserted.

At this moment in time the crane and the rig are being moved to the top section of the site nearer to the railway station to allow for the sheet piling of Blocks A & B, this process will continue until mid August when my next visit is due. A new contractor will be brought in after this to do the foundation bearing piles which will continue through to the end of September.

The photographs I have taken (the sunshine makes all the difference) below show and tell you more…

Where possible the concrete broken out from the base of the gasholder has now been crushed and reused on site to form the piling mat, additional crushed concrete is brought in as well.

The Echo Barrier used on site is scientifically developed by leading acoustic engineers, acoustic barriers are the most effective temporary noise control solutions on the market. They typically reduce noise energy by up to 99%, and are lightweight, weatherproof and adaptable to any setting.

Piling is an essential part of building works to ensure strong foundations and prevent the risk of any future subsidence or ground movement.

If you are interested to know more about purchasing an apartment, follow this link to Robert Leech, the Estate Agents for this development by St William, part of the Berkeley Group

To keep up to date with my blogs and to sign-up to my monthly round-up newsletter please scroll down to the ‘Subscribe to Our Newsletter’ button below to enter your contact email address.

I’ll be back next month with further updates, watch this space for further developments.

Thanks for reading, bye for now.

Stella

To read other previous blogs these can be found on the ‘Featured’ blogs below by using the arrows on the right to scroll through the past 30 blogs.

 

Oxted Gasholder - Courtyard Gardens Build - June 2019

On site at the Courtyard Gardens housing development for 111 luxury apartments.

On site at the Courtyard Gardens housing development for 111 luxury apartments.

Welcome to this months June blog about the St William Courtyard Gardens development here in Oxted, this blog is number 6, previous ones can be found here.

For my regular readers and locals, you will be aware that the gas holder that once stood on this site for over 50 years is no more, its removal has made way for the construction of 111 luxury apartments due for completion summer 2021, my regular monthly blogs will keep you updated about the progress.

The buildings works are beginning to take shape, the previous two bases where the gas holders once sat are less visible now. This photograph taken on 11 June 2019.

The buildings works are beginning to take shape, the previous two bases where the gas holders once sat are less visible now. This photograph taken on 11 June 2019.

Moving on…

I look forward to my monthly site visits because each time I photograph I can see a vast difference that never ceases to amaze me, and this time was no exception. I know very little (maybe nothing) about the building process and find it fascinating to see the different processes involved, from the excavation, to the soil examination, to the air purifiers, that intermittently blast a mist of a fragrance that is reminiscent of freshly ironed cotton sheets, into the atmosphere to dissipate any potential soil odours. A series of vibration and noise mechanisms are in place to monitor in real time the vibration and noise emitted from activities on site, and dust suppression is in place to settle any excess from spreading.

The remaining rim of the base of the gas holder is over one metre wide and over 5 metres deep/high. During the removal process we have heard a tapping sound during working hours (my studio backs onto the site), which has been the result of the gradual destruction of the concrete to make way for the building works to take place. All of the hardcore on site is recycled for use during the building process.

The photographs below show the preparation of the ground works before the sheet piling takes place next week during a six week period. There is no longer gas on the site as all essential gas equipment has been relocated, but occasionally people may notice some smells as the next phase of groundworks begins, but hopefully the air fragrance will be sufficient to destroy this. There will also be increased noise and vibration during this period. I will be on site in July to photograph this next stage.

The photographs below give you a sense of what it is like.

Each time I am on site I meet a different team of contractors as the development grows, but the two people from St William, who have remained constant are Joe Pallister the Project Manager and Ness Kingham, the lovely Site Manager, who accompanies me on my visits and tells me more about the build process each time, very educational. On this particular occasion the heavy rain over the past few weeks was one of the topics of conversation as it had made the site very muddy and slippery, a pump was needed to drain the excess water that had collected at the lowest point, it looks like we have experienced the wettest June on record!

The photographs show different machinery that is required on site to excavate the soil, move rubble and prepare the surface for the next stage. What once looked like a familiar space to me no longer feels or looks how l once remembered it.

If you would like to keep up to date and sign-up to my monthly round-up newsletter please scroll down to the ‘Subscribe to Our Newsletter’ button below to enter your contact email address.

I’ll be back next month with further updates, watch this space for further developments.

Thanks for reading, bye for now.

Stella

To read other previous blogs these can be found on the ‘Featured’ blogs below by using the arrows on the right to scroll through the past 30 blogs.